Installation of outdoor fitness equipment

Aug. 17, 2021

Installation of outdoor fitness equipment


With the continuous development of today's society, outdoor fitness equipment has become more and more popular among the people, and its installation has gradually been taken seriously. In fact, outdoor fitness equipment installation is very simple, basically divided into the following four installation:


First: DIRECT-BURIED INSTALLATION: direct-buried equipment installation according to the height is divided into three: 1 meters below, 1-2 meters between 2 meters above, the three height equipment installation method is the same:

1. EXCAVATION: Pit Size is 410 * 410 * 600 mm; 

2. PIT BOTTOM CUSHION CONCRETE: pit bottom cushion concrete thickness is 100 mm, concrete proportion is (cement: Sand: Stone)1:2:3.5; 

3. Buried equipment: Equipment placed in the center of the pit, adjusted to vertical column and ground, buried Mark Line and ground level; 

4. POURING CONCRETE: pour concrete around the column of equipment, fill height is 400mm, concrete ratio is (cement: Sand: Stone)1:2:3.5; 

5. Backfill layer: fill 100 mm backfill layer on top of concrete layer to reduce the cushion of accidental fall. 

6. Use of equipment: 7 days after installation and maintenance, the equipment can be used.

Note: The size of Pit Foundation and filling height will be different for equipment of different height. The details can be based on the mark line of Ground Vein of equipment.


Second: Embedded installation: embedded equipment installation according to embedded parts shape is divided into three: J, T, well, the three shapes of embedded parts of the equipment installation method is the same

2. PIT BOTTOM CUSHION CONCRETE: pit bottom cushion concrete thickness is 100 mm, concrete proportion is (cement: Sand: Stone)1:2:3.5; 

3. Insert the embedded parts: the equipment is placed in the center of the foundation pit, adjusted to the vertical column and the ground, the connection between the equipment and the embedded parts is kept level with the ground; 

4. POURING CONCRETE: pour concrete around the column of equipment, fill height is 400mm, concrete ratio is (cement: Sand: Stone)1:2:3.5; 

5. Backfill layer: fill 100 mm backfill layer on top of concrete layer to reduce the cushion of accidental fall. 

6. Connecting equipment and embedded parts: the column connecting hole of the equipment is inserted into the exposed thread part of the embedded parts, and the anti-theft bolts are tightened. 

7. Use of equipment: 7 days after installation and maintenance, the equipment can be used.

Note: different equipment, different embedded parts, dug pit size and fill height will be different, the details can be based on embedded parts


Third: Flange embedded installation: flange embedded equipment installation method is the same, but buried depth is different, the following as an example of a depth:

1. PIT EXCAVATION: pit size is 500 * 300 * 500 mm; 

2. PIT BOTTOM CUSHION CONCRETE: pit bottom cushion concrete thickness is 100 mm, concrete proportion is (cement: Sand: Stone)1:2:3.5; 

3. Connecting equipment and embedded parts: the connecting hole of the equipment is aligned with the connecting hole of the embedded parts, the connecting hole is inserted with the screw, the locking nut; 

4. Buried equipment: Equipment placed in the center of the pit, adjusted to vertical column and the ground, equipment and embedded parts of the connection to keep level with the ground; 

5. POURING CONCRETE: pour concrete around the column of equipment, fill height is 300 mm, concrete ratio is (cement: Sand: Stone)1:2:3.5;

6. Backfill: a 100 mm backfill is applied to the concrete layer to reduce the impact of accidental falls. 

7. Use of equipment: 7 days after installation and maintenance, the equipment can be used.

Note: The buried depth will be different for different equipment. For details, please refer to the buried mark line of the equipment


Fourth: Expansion installation: expansion equipment installation method is the same

1. Mounting Holes: There are corresponding mounting holes at the edges and corners of the frame type fitness equipment, the diameter is 15 mm; 

2. DRILLING: The length of the expansion bolt is 6-11 cm, the diameter is 12 mm, the diameter is 16 mm, the electric hammer head drilling is required, the depth is recommended to extend 5 mm than the length of the expansion bolt; 

3. Installation ground requirements: The installation ground requirements are hardened cement, or the installation hole part of 400 mm * 500 mm range for the cement ground; 

4. Installation: The installation hole of the fitness equipment is opposite to the expansion bolt and is tightened by the nut. 

5. The use of equipment: installed after the completion of anti-theft nuts can be used.

Note: The installation method of expandable equipment in outdoor fitness equipment is very simple and can be used after installation, but for the safety of long-term use, it is not recommended to use expandable installation